Causes of Delays in Construction Projects in Faryab/Afghanistan

Authors

  • Nurafzal Qaytmas Department of Civil Engineering, Faculty of Engineering, Faryab University, Faryab, AFGHANISTAN

Keywords:

Construction Projects, Delay Causes, Faryab

Abstract

One of the most important goals in construction projects management is to complete the project in a certain time. Projects success can be considered as doing work at a reasonable cost, quality and at the right time and delay is one of the most important and frequent phenomena in construction projects and in terms of cost, quality and time has a negative impact on project success.

From in-depth literature studies, twenty-three causes of delay were identified. Questionnaires were then developed and sent to 50 carefully selected construction industry stakeholders including: clients, contractors, and consultants in Faryab/Afghanistan.

In this research, the causes of delays in construction of Maimana city urban asphalt road 32.805 km projects have been identified. Numerous factors such as: insecurity, corruption, low experience of the contractors technical team, late payment of invoices by the project owner, poor management and monitoring of the site by the contractor and Contractor's joint venture can cause delays in projects.

 

Downloads

Download data is not yet available.

References

Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Delay in public utility projects in Saudi Arabia. International Journal of Project Management, 17(2), 101–106. https://doi.org/10.1016/S0263-7863(98)00020-9

Long, N. D., Ogunlana, S., Quang, T., & Lam, K. C. (2004). Large construction projects in developing countries: A case study from Vietnam. International Journal of Project Management, 22(7), 553–561. https://doi.org/10.1016/j.ijproman.2004.03.004

Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of Project Management, 21(5), 321–326. https://doi.org/10.1016/S0263-7863(02)00055-8

Manavazhi, M. R., & Adhikari, D. K. (2002). Material and equipment procurement delays in highway projects in Nepal. International Journal of Project Management, 20(8), 627–632. https://doi.org/10.1016/S0263-7863(02)00027-3

Ndekugri, I., Braimah, N., & Gameson, R. (2008). Delay Analysis within Construction Contracting Organizations. Journal of Construction Engineering and Management, 134(9), 692–700. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:9(692)

Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: Traditional contracts. International Journal of Project Management, 20(1), 67–73. https://doi.org/10.1016/S0263-7863(00)00037-5

Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010

Saleh Al Hadi Tumi, Abdelnaser Omran, Abdul Hamid Kadir Pakir. (2009). Causes of Delay in Construction Industry in Libya. The International Conference on Economics and Administration, Faculty of Administration and Business, University of Bucharest, Romania ICEA – FAA Bucharest.

Trauner, T. J. (2009). Construction Delays: Understanding Them Clearly, Analyzing Them Correctly. Elsevier Science. https://books.google.co.in/books?id=oAXtvyysljkC

Downloads

Published

2020-11-30

How to Cite

Nurafzal Qaytmas. (2020). Causes of Delays in Construction Projects in Faryab/Afghanistan. International Journal for Research in Applied Sciences and Biotechnology, 7(6), 72–77. Retrieved from https://ijrasb.com/index.php/ijrasb/article/view/298